How to Apply Power to the System

This procedure instructs on how to apply power to a system that has already been installed. For initial start-up instructions, see InfraStruXure 80kW Installation and Start-Up.

1. Set the upstream utility, and, if applicable, the bypass input and cross tie utility circuit breaker to ON.

A B X

1.Set the Main Input (A) switch on the PDU to ON.

2. Close (turn ON) the Q1 circuit breaker on the PDU to apply power to the UPS.

3. If applicable, set the Q10 Bypass Input (B) switch on the PDU to ON.

InfraStruXure System—Installation and Start-Up

75

Page 85
Image 85
American Power Conversion InfraStruXureTM System manual How to Apply Power to the System