Exchange Side Panels
Before installing the InfraStruXure PDU, Symmetra PX UPS, and Battery Enclosure, you will need to exchange side panels so that the adjacent panels will have matching holes for joining the enclosures together and for routing input and output wiring between them. The following side panels will need to be exchanged:
•Adjacent side panels of a PDU and UPS
•Adjacent side panels of a Battery Enclosure and a UPS
•Adjacent side panels of two Battery Enclosures
To exchange side panels:
1. Detach the ground wires from the side panels that you will be exchanging.
20 | InfraStruXure |