Site Planning: Basic Installation Procedure

7.Connect utility conductors to the PDU.

A licensed electrician must connect utility power.

For instructions, see Certified Electrician’s Instructions (990-1469A) included with your InfraStruXure PDU documentation.

See also

8. Connect AC power and control wiring.

See page 26 for detailed instructions.

9. Connect DC power wiring.

See page 30 for detailed instructions.

10. Connect an EPO switch to the PDU user connection plate.

See page 33 for detailed instructions.

11. Connect user input contacts and relay outputs to the PDU user connection plate, if applicable.

See page 37 for detailed instructions.

12. Install Shielding Troughs, Shielding Partitions, and Cable Ladders.

See also

See also

See page 39 for general information.

For detailed information and grounding instructions, see the instruction sheet included with the Shielding Troughs and Shielding Partitions (990-1393B).

For more information on installing and grounding the Cable Ladders see the instruction sheet included with the cable ladders (990-1576).

13.Install the Rack Automatic Transfer Switches (ATS), Rack Power Distribution Units, and other InfraStruXure rack-mount devices.

For instructions, see the manuals included with your Rack ATS, Rack PDU, or other InfraStruXure rack-mount device.

See also

14. Route and attach power cables to RDPs and to each Rack ATS and/or Rack PDUs.

See page 41 for detailed instructions.

15. Route and attach communication cables to the InfraStruXure Manager hub (or switch).

See page 46 for detailed instructions.

InfraStruXure System—Installation and Start-Up

15

Page 25
Image 25
American Power Conversion InfraStruXureTM System manual Licensed electrician must connect utility power