Installing connector cables between auxiliary cabinet and MDF
Installing connector cables between auxiliary cabinet and
MDF
Auxiliary equipment that connects to the MDF can be mounted inside the auxiliary cabinet. The equipment connects to an
To install connector cables between the auxiliary cabinet and the main distribution frame:
1.Install “D” rings on the wall between the cable slack manager and the terminal/connecting blocks mounted on the MDF.
2.Install a
3.Labels should be positioned so the cabinet connector retainers do not obscure them.
4.At the rear of the auxiliary cabinet, connect 1 end of the connector cable to the assigned connector.
5.Route the cable down the rear of the cabinet and through the cable slack manager to the MDF.
6.At the MDF, connect the other end of the cable to the assigned terminal/connecting block connector.
7.Store the excess cable in the cable slack manager.
8.Repeat Steps 2 through 6 until all cables are installed.
Figure 16: Self-stick label on 25-pair cable connector
Issue 3 January 2008 39