Chapter 5: Management with WebPAM PRO

Viewing Current Background Activities

To view the current background activities:

1.Click the Subsystem icon in Tree View.

2.Click the Background Activities tab in Management View. A list of current background activities appears, including:

Rebuild

PDM – Predictive Data Migration

Synchronization

Redundancy Check

Migration

Transition

Initialization

Media Patrol

Making Background Activity Settings

To make settings for background activities:

1.In Tree View, click the Subsystem icon.

2.From the dropdown menu on the Background Activities tab, choose Settings.

3.Click the dropdown menu to choose a priority of Low, Medium, or High for the following functions:

Rebuild – Rebuilds the data from a failed drive in a disk array

Synchronization – Checks the data integrity on disk arrays

Initialization – Sets all data bits in the logical drive to zero

Redundancy Check – Checks, reports and can correct data inconsistencies in logical drives

Migration – Change RAID level or add physical dries to disk arrays

PDM – Looks for bad blocks the physical drives of disk arrays

Transition – Returns a revertible spare drive to spare status

The rates are defined as follows:

Low – Fewer resources to activity, more to data read/write.

Medium – Balance of resources to activity and data read/write.

High – More resources to activity, fewer to data read/write.