Chapter 2 Installation Setup
This chapter explains how to set up and install the Eaton 9170+ cabinets:
SSetup, including clearances and location requirements
SCaster cart installation (for 3- and
SStabilizer bracket installation (for
S
SFloor anchor kit installation
SMoving the cabinets
Equipment Clearances
All cabinet sizes require the following clearances to allow for servicing and adequate ventilation:
SSides: 15.2 cm (6”)
STop and back: 30.5 cm (12”)
SFront: 91.5 cm (36”)
If flexible conduit connects the UPS to the service input and load distribution panels, you may be able to gain access for servicing by moving the UPS. If this is the case, you must still leave 30.5 cm (12”) clearance at the back and 15.2 cm (6”) at the sides of the UPS for ventilation.
NOTE Do not block the ventilation holes on each side and the back of the cabinet.