INSTALLATION SETUP

5.If installing the 3- or 6-slot cabinet in a rack, see ”Rack-Mount Installation (Three- and Six-Slot Cabinets)” on page 14 to install the cabinet in the rack.

6.If you are installing an external battery cabinet, continue to “Battery Cabinet Installation” on page 61.

If you do not have an external battery cabinet, continue to “UPS Startup” on page 67 for plug-receptacle units. For hardwired units, continue to “UPS with Bypass Electrical Installation” on page 19 or “UPS Electrical Installation” on page 39.

Nine- and Twelve-Slot Cabinets

C A U T I O N

Do NOT lower the casters or attempt to move the cabinet with the power or battery modules installed.

To set up 9- or 12-slot cabinets:

1.Lower the four cabinet casters (one at each corner of the cabinet base) by using a 1/2” hex-style socket wrench to turn each bolt clockwise.

2.With all casters fully extended, carefully roll the cabinet down the ramp to its intended operating location.

NOTE For 12-slot cabinets. Before moving the 12-slot cabinet to its intended operating location, see “Stabilizer Bracket Installation (Twelve-Slot Cabinet Only)” on page 13 to install two stabilizer brackets.

3.Stabilize the cabinet in its operating location by turning the four caster bolts counter-clockwise until the cabinet rests on the floor. Place a plastic cap into each bolt access hole.

NOTE If the floor is uneven and the cabinet is tilted or unstable, you may need to place a thin steel plate under a corner. Do not use the caster bolts to level the cabinet.

4.If an optional floor anchor kit is included for extra stability, see ”Floor Anchor Kit Installation” on page 16 to install the floor anchor brackets.

Eaton 9170+ UPS (3–18 kVA) User's Guide S 164201393 Rev E www.eaton.com/powerquality

11

Page 17
Image 17
Eaton Electrical ASY0529, ASY0673, ASY0567, ASY0674 manual Nine- and Twelve-Slot Cabinets