Figure 34 (page 84) shows the overview of the operation and the status of the cross-subsystem paths. When you delete the current cross-subsystem paths (A and B) and add new cross-subsystem paths (C and D), you cannot delete both the current cross-subsystem paths (A and B) in one operation because at least one current path that functions normally has to be configured. In this case, you need to delete the cross-subsystem path A and add the cross-subsystem path C, and then apply the setting. After that, you need to delete the cross-subsystem path B and add the cross-subsystem path D.
Figure 34 Overview of Operation to Replace All the Current Cross-subsystem Paths with Newly-added Cross-subsystem Paths
To replace all the current
1.Execute the Disconnect Paths command on the
2.Disconnect the cable that the
3.Cancel the configuration of the
4.Click Apply to apply the settings of the
5.Make sure the status of the
At this point, the
Take the following steps to delete the
6.Execute the Disconnect Paths command on the