Chapter 4 Commissioning of UPS
Step 5 : After the UPS transfers from bypass to inverter, the bypass indicator turns off, and the inverter and the load indicator turns on. The transfer may fail if the phase rotation of bypass and inverter output are different.
During operation, if the AC power recovers after failure, the rectifier will restart automatically after some time. If the UPS transfer to generator power, the monitoring system will determine the quality of the generator supply. The time it takes to determine this, ranges from 1 second to 255 seconds.
After startup, use the keypad to set the functions of the UPS.
Note
Power failure means the line to neutral voltage is lower than 120V or the Line to Line voltage is lower than 208V over 10 msecs.
4.2 Setting the functions
The methods of setting the functions will be described in details in Chapter 5.
This chapter only introduces the setting that relates to commissioning.
The user enters the menu of “set functions” shown in the figure below.
12:50:30 | |||||
Inv. On |
| Units 2/4 |
| ID: 1 | |
Out |
| Language |
| Chinese | |
Local |
| Chinese | English | ||
System | Com. Adress Set | 1 | |||
Battery |
| 1 |
|
|
|
Records | Date & Time Set |
|
| ||
Settings |
| 2001£ | |||
Input Breaker Closed11£ | |||||
Byp. Breaker Closed 11£ | |||||
Mains Volt. Abnormal | 11£ | ||||
UPS in Battery Mode | 11£ | ||||
Battery low |
| 11£ |
Fig. 4-1 Function Setup Menu
Language selection : select “Chinese” or “English” as shown in Figure
Address setup : set the address of this UPS in the monitoring system as shown in Figure
Date and Time setup : format is
38