Chapter 2 Cabinet Installation

2.4Transportation

1.Hoisting the UPS

Prepare four cables of length 1.5 m and the weight bearing capacity of each cable of 1.5 tons. The UPS has four lifting rings and should be installed at the top of the

UPS

2. Transportatio with Forklift

The UPS can be raised by forklift in four directions – front, back, left and right. But the transportation distance should not exceed 10 m.

2.5 Positioning of UPS

The UPS cabinet exerts its weight on the floor through four castors. If the load bearing capacity of the floor is inadequate, add auxiliary equipment to distribute the weight over a larger area, such as a big iron sheet or increasing the number of supporting castor wheels.

Note

As the UPS is cooled from the bottom, at least 10 cm space should be left at the bottom of the UPS for ventilation

There are three kinds of positioning methods:

1. Non-Fixed position

Place the UPS directly on the flat ground . The ground should be made of Industrial cement. Level the UPS by lowering and adjusting the leveling bolt at the base of the UPS.

4 M20 screws for levelling feet

Figure 2-5