SEDIMENT TRAPS

A sediment trap should be installed as close to the inlet of the water heater as practical at the time of water heater installation. The sediment trap should be either a tee fitting with a capped nipple in the bottom outlet or other device recognized as an effective sediment trap. If a tee fitting is used, it should be installed in conformance with one of the methods of installation shown in Figures 12 and 13.

Contaminants in the gas lines may cause improper operation of the gas control valve that may result in fire or explosion. Before attaching the gas line be sure that all gas pipe is clean on the inside. To trap any dirt or foreign material in the gas supply line, a drip leg (sometimes called a sediment trap) must be incorporated in the piping. The drip leg must be readily accessible. Install in accordance with the “Gas Piping” section. Refer to the current edition of the Natural Gas and Propane Installation Code (CAN/CSA B149.1).

FIGURE 14.

Filling the Water Heater

Never use this water heater unless it is completely full of water. To prevent damage to the tank, the tank must be filled with water. Water must flow from the hot water faucet before turning “ON” gas to the water heater.

To fill the water heater with water:

1.Close the water heater drain valve by turning handle to the right (clockwise). The drain valve is on the lower front of water heater.

2.Open the cold water supply valve to the water heater.

NOTE: The cold water supply valve must be left open when the water heater is in use.

3.To insure complete filling of the tank, allow air to exit by opening nearest hot water faucet. Allow water to run until a constant flow is obtained. This will let air out of the water heater and the piping.

4.Check all water piping and connections for leaks. Repair as needed.

VENT PIPE ASSEMBLY

There are three parts of the vent pipe assembly that connect the water heater exhaust (located on lower back side of water heater) to inlet of the blower assembly (mounted on top of water heater) as shown in Figure 1. These parts will need to be assembled according to these instructions.

Assemble Vent Pipe Assemblies #1, #2 and #3 (See Figure 1) prior to cementing. The preferred orientation of Vent Pipe Assembly #1 (Condensate U-Assembly) is shown in Figure 16. However this assembly may be rotated to a different orientation as needed for the specific installation requirements. Note the rotational orientation of each part by marking a line several inches long across the joints.The long tube of Vent Pipe Assembly #2 should be approximately vertical. If it is found that either of the two pieces of pipe in Vent Pipe Assembly #2 are too long for proper fit-up, then remove as little material as possible to improve the fit-up. Keep in mind that the pipes will insert slightly further into the elbows when cement is applied as it acts as a lubricating agent. The vertical distance from the bottom of the Condensate U-Assembly to the floor that supports the water heater should be approximately 0.25” (0.64 cm), see Figure 16. Disassemble the parts and cement back together using the alignment marks. After the cement dries, attach the assembly to the blower and the water heater exhaust using the supplied rubber boots and hose clamps.

A condensate trap is incorporated in the bottom of this vent pipe assembly. See the CONDENSATE section of this manual for further details.

VENTING

18

Image 18
Contents Power Vented GAS Models W/HOT Surface Ignition Whenever maintenance adjustment or service is requiredSafe INSTALLATION, USE and Service ApprovalsImportant Definitions General Safety Information General Safety Information Table of Contents To Install or Operate the Water Heater Qualified Installer or Service AgencyPreparing for the Installation IntroductionTypical Installation Replacement Parts and Deliming ProductsRelief Valve Elbow Access Door Condensate Hose and Drain PAN Mixing Valves Less Severe Burns 2nd & 3rd Degree Most Severe BurnsLocating the NEW Water Heater Facts to Consider About the LocationInsulation Blankets Air REQUIREMENTsFresh Air Openings For Confined Spaces Unconfined SpaceConfined Space Outdoor Air Through Two OpeningsOutdoor AIR Through TWO Horizontal Ducts Outdoor AIR Through TWO Vertical DuctsAIR from Other Indoor Spaces Water Piping Installing the NEW Water HeaterChemical Vapor Corrosion Space Heating and Potable Water System Temperature-Pressure Relief Valve Thermal Expansion Valve and Pipe Insulation High Altitude Installation Valve Discharge Pipe RequirementsGAS Piping with Flexible Connector GAS Piping with ALL Black Iron Pipe to GAS ControlFilling the Water Heater Vent Pipe AssemblySediment Traps VentingTermination Clearances Sidewall Power Vent Vent Pipe TerminationPlanning the Vent System CondensateBreathing Hazard Carbon Monoxide Gas Blower Assembly Installation Vent Terminal INSTALLATION, SidewallPower Vent Wiring Schematic Figure Vent Termination FigureInstallation of Vent SYSTEM, Sidewall Installation of Vertical Vent SystemVent Attenuation Assembly Installation Vertical VAA Installations RecommendedInch vent Vertical VAA Installations Inch vent Horizontal VAA InstallationsCould cause illness, asphyxiation and/or even death Page Temperature Regulation Water TemperatureFor Your Information Start UP ConditionsOperational Conditions Periodic Maintenance Anode ROD InspectionTemperature-Pressure Relief Valve Test Draining and FlushingService To Drain the Water Heater Storage TankTo Flush the Water Heater Storage Tank Leakage Checkpoints Repair Parts List Troubleshooting Guidelines Trouble ShootingLED Status Problem Solution LED Status Problem Solution Troubleshooting Guidelines Troubleshootinotesg Guidelines Troubleshootinotesg Guidelines Conditions and Exceptions Service and Labor ResponsibilityClaim Procedure Limitation on Implied WarrantiesGSW Water Heating Hill Street West Fergus, on Canada N1M CHAUFFE-EAU AU GAZ Résidentiel ImpriméINSTALLATION, Utilisation ET Service EN Toute Sécurité ApprobationsDéfinitions Importantes Avertissement Information DE Sécurité Générale AVERTISSEMENT Emplacement DU Nouveau CHAUFFE-EAU Table DES MatièresInstallateur ou organisme de service qualifié Préparation pour l’installationInstallation Type Piècesde Rechange ET Produits DE DétartrageTuyau DE Condensat ET BAC DE Vidange Mélangeurs TableauEmplacement DU Nouveau CHAUFFE-EAU Faits à prendre en considération concernant l’emplacementProtections Thermiques Quantité d’air NécessaireOuvertures d’air frais pour espaces clos Espaces non closEspace Clos Air extérieur à travers deux ouverturesAIR Externe À Travers Deux Conduits Horizontaux AIR Externe À Travers Deux Conduits VerticauxAIR Provenant D’AUTRES Espaces Intérieurs Conduites d’eau Installation DU CHAUFFE-EAUCorrosion DE Vapeur Chimique Chauffage DES Locaux ET Systèmes D’EAU PotableExpansion thermique Soupape de décharge à sécurité thermiqueInstallation À Haute Altitude Pressure Relief Valve thermique. discharge outletConduite de gaz Bacs DE SédimentationRemplissage du chauffe-eau Ensemble Tuyau DE VentilationVentilation Terminaison DU Tuyau DE Ventilation Ventilation À AIR PulséSi un tuyau de ventilation de 2 po est utilisé Planification DU Système DE VentilationCondensat Si un tuyau de ventilation de 3 po ou 4 po est utiliséInstallation DE L’ENSEMBLE DE LA Soufflante Installation DU Terminal D’ÉVENT, Paroi LatéraleTerminaison DE L’ÉVENT Figure AvertissementSchéma DU Câblage DE L’ÉVENT À AIR Propulsé Figure Installation DU Système DE VENTILATION, Paroi Latérale Installation DU Système DE Ventilation VerticalInstallation DE L’ENSEMBLE D’ATTÉNUATION DE L’ÉVENT Installations verticales de l’EAE RecommandéesÉvent de 4 po Installations verticales d’EAE Évent de 3 po Installations horizontales d’EAEÉvent de 3 po Installations verticales d’EAE Évent de 4 po Installations horizontales d’EAEQUE Faire EN CAS D’ODEUR DE GAZ NE PAS Tenter D’ALLUMER LE Brûleur À LA MainRégulation DE Température Bouton « Cooler » plus froid jusqu’à ce que le réglageConditions DE Mise EN Service Pour Votre InformationConditions Opérationnelles Entretien Périodique Inspection DE LA Tige D’ANODEDdanger Test de soupape de décharge à sécurité thermiqueVidange ET Rinçage Pour Vidanger LE Réservoir DE Stockage DU CHAUFFE- EAUPour Rincer LE Réservoir DE Stockage DU CHAUFFE-EAU Points DE Vérification DES Fuites Liste DE Pièces DE Rechange Statut DEL Problème Solution Directives DE Dépannagep GEDépannage ’assurer que le capteur de flamme établit un bon contact Problème Cause Solution Directivesmarquesde Dépannage Directivesmarquesde Dépannage Garantie Limitée Pour GAZ Résidentiel