Stacking Recommendations

The purpose of this section is to collect notes on recommended procedures and expected behavior of stacked managed switches. Procedures addressed initially are listed below.

Initial installation and power-up of a stack.

Removing a unit from the stack

Adding a unit to an operating stack

Replacing a stack member with a new unit

Renumbering stack members

Moving the master to a different unit in the stack

Removing a master unit from an operating stack

Merging two operational stacks

Preconfiguration

Upgrading firmware

Migration of configuration with a firmware upgrade

General Practices

When issuing a command (such as move management, or renumber), it is recommended that the command has fully completed before issuing the next command. For example, if a reset is issued to a stack member, use the show port command to verify that the unit has re-merged with the stack, and all ports are joined before issuing the next command.

When physically removing or relocating a unit, always power down the unit before disconnecting stack cables.

When reconnecting stack cables, connect them before powering up the unit, if possible, and insure a good connection by tightening all connector screws (where applicable).