10.13 Set Up I/O Network

Figure 10-22- Network Setup Menu

To start the setup on the I/O Network, access the Net- work Setup menu:

1.Press to open the Main Menu

2.Press (System Configuration)

3.Press (Network Setup)

The Network Setup menu displays four options:

Network Summary

Connected I/O Boards & Controllers

Router Setup

Controller Associations

For the total (E2) devices online or offline, status, setup screens, changing board or controller names, config- uring and commissioning devices, deleting a device, and viewing detailed status screens of controllers, select Net- work Summary.

For the number of I/O Network devices (16AIs,8ROs, etc.) associated with each controller online and offline, select Connected I/O Boards & Controllers.

To set up a router, select Router Setup. For more information on routers and repeaters, refer to the Router and Repeater Installation Guide (P/N 026-1605).

For CC-100 circuit associations, select Controller Associations.

10.13.1 Specify Number of Boards

Specify the number of boards from the Connected I/O screen:

1.Press to open the Main Menu

2.Press (System Configuration)

3.Press (Network Setup)

4.Press (Connected I/O Boards & Controllers)

Figure 10-23- Connected I/O Screen (RX version)

Boards on the I/O Network

16AI Boards Enter the number of 16AI analog input boards on this E2’s I/O Network.

8RO Boards Enter the number of 8RO relay output boards on this E2’s I/O Network.

8DO Boards Enter the number of 8DO digital out- put boards on this E2’s I/O Network.

4AO Boards Enter the number of 4AO analog out- put boards on this E2’s I/O Network.

IRLDS Controllers Enter the number of leak detec- tor units on this E2’s I/O Network.

(Options will vary depending on the type of controller used.)

10.13.2 Checking Online Status

Figure 10-24- Network Summary Screen

You can check all boards that are on either the Echelon Network (E2 controllers) or the I/O Network from the Net-

Set Up I/O Network

Quick Start 10-15

Page 129
Image 129
Emerson E2 operation manual Set Up I/O Network, Specify Number of Boards, Checking Online Status