Setting up the Analyzer20

General Settings

Below you will find a step-by-step example on how to change wiring configuration to 3- phase Wye IT (IT = Interrupted Terra = Interrupted Ground).

c SETUP

The active configuration is indicated behind Config. Config is highlighted indicating that this item can be adjusted when you press the ENTER key. The belonging configuration symbol is shown on the right side of the screen.

d ENTER

The screen shows 4 wiring configurations; 3- phase Wye IT configuration is not among them. Press F2 to access a second screen with 4 other configurations.

e F2

The second screen incorporates 3-phase Wye IT (3φ IT) configuration.

f

Use the arrow keys to highlight 3φ IT. Press F5 to confirm the selection.

20-5

Page 99
Image 99
Fluke 435 user manual 20-5