Installing and Configuring the Edge Switch 2/32
4.Verify that the SFP optical transceivers are installed as required for your installation.
5.Connect the U.S. or
WARNING: An
6.Connect the remaining ends of the AC power cords to separate facility power sources that provide
7.Turn on the power. Two power switches are on the back of the unit. Turn on both switches. The unit powers on and performs
a.The green power (PWR) LED on the front panel turns On.
b.The amber system error (ERR) LED on the front panel flashes momentarily while the switch is tested.
c.The green LEDs associated with the Ethernet port flashes momentarily while the port is tested.
d.The green and amber LEDs associated with the ports flash momentarily while the ports are tested.
8.After successful POST completion, the green power (PWR) LED remains ON and all other front panel LEDs turn OFF.
9.If a POST error or other malfunction occurs, refer to the hp StorageWorks edge switch 2/32 service manual to isolate the problem.
Rack-Mount Installation
To install the switch in a