Commissioning
Commissioning Procedure
This section provides the procedure necessary to safely and correctly commission a PV100S inverter.
| Important: It is important to record any issues encountered while following this | |
| procedure. | |
Summary | To commission the PV100S: | |
| 1. Ensure the Verification Tests have been completed and have passed | |
| successfully. See the PV100S 100 kW | |
| Planning and Installation Manual, Section 4. | |
| 2. Begin the PV100S Commissioning Procedure as described in detail further in | |
| this section. The steps are summarized below. | |
| a) | Start the GUI and open the PV100S Commissioning Procedure file. |
| b) | Record the Serial Number. |
| c) | Verify AC and DC Voltages. |
| d) | Inspect Lower Inductor Enclosure. |
| e) | Apply Grid Voltage. |
| f) | Check the Front Panel Display. |
| g) | Establish communications with the GUI. |
| h) | Confirm Operational Parameters (AC, DC and Power Tracker). |
| i) | Verify Door Interlock Functions. |
| j) | Perform the Matrix Test. |
| k) | Operate Inverter. |
3. Submit the Test report and warranty form to Xantrex See “PRODUCT REGISTRATION” on page
Starting the Commissioning Test File
1.Start the Xantrex Solar Graphical User Interface (GUI) program.
a)Once the application has started, select “GENERAL PROCEDURES” from the “TOOLS”
b)In the “SELECT FILES” dialog box, choose “PV100S COMMISSIONING TEST” and click the OPEN button.
2.Verify that both the AC (S1) and DC (S2) Disconnect switches are open.
3.Verify the ON/OFF switch (S3) is in the OFF position.
4.Once you finish these tasks, go back to the GUI and click on the check box to indicate the task is complete. Go to the next step by clicking on the "NEXT" button.
152379 Rev B |