Xantrex Technology PV100S-208 manual Commissioning Procedure, Starting the Commissioning Test File

Models: PV100S-208

1 124
Download 124 pages 2.86 Kb
Page 80
Image 80
Commissioning Procedure

Commissioning

Commissioning Procedure

This section provides the procedure necessary to safely and correctly commission a PV100S inverter.

 

Important: It is important to record any issues encountered while following this

 

procedure.

Summary

To commission the PV100S:

 

1. Ensure the Verification Tests have been completed and have passed

 

successfully. See the PV100S 100 kW Grid-tied Photovoltaic Inverter

 

Planning and Installation Manual, Section 4.

 

2. Begin the PV100S Commissioning Procedure as described in detail further in

 

this section. The steps are summarized below.

 

a)

Start the GUI and open the PV100S Commissioning Procedure file.

 

b)

Record the Serial Number.

 

c)

Verify AC and DC Voltages.

 

d)

Inspect Lower Inductor Enclosure.

 

e)

Apply Grid Voltage.

 

f)

Check the Front Panel Display.

 

g)

Establish communications with the GUI.

 

h)

Confirm Operational Parameters (AC, DC and Power Tracker).

 

i)

Verify Door Interlock Functions.

 

j)

Perform the Matrix Test.

 

k)

Operate Inverter.

3. Submit the Test report and warranty form to Xantrex See “PRODUCT REGISTRATION” on page WA–3.

Starting the Commissioning Test File

1.Start the Xantrex Solar Graphical User Interface (GUI) program.

a)Once the application has started, select “GENERAL PROCEDURES” from the “TOOLSpull-down menu.

b)In the “SELECT FILES” dialog box, choose “PV100S COMMISSIONING TEST” and click the OPEN button.

2.Verify that both the AC (S1) and DC (S2) Disconnect switches are open.

3.Verify the ON/OFF switch (S3) is in the OFF position.

4.Once you finish these tasks, go back to the GUI and click on the check box to indicate the task is complete. Go to the next step by clicking on the "NEXT" button.

3–2

152379 Rev B

Page 80
Image 80
Xantrex Technology PV100S-208 Commissioning Procedure, Starting the Commissioning Test File, To commission the PV100S