Preventative Maintenance
Maintenance Safety
Prior to following any Maintenance Procedures, follow the System Shutdown and
Operational Safety Procedures
Never work alone when servicing this equipment. A team of two is required until the equipment is properly
WARNING: Shock Hazard
Review the system schematic for the installation to verify that all available energy sources are
De-Energize/Isolation Procedure
The following procedure should be followed to
WARNING: Shock Hazard
The terminals of the DC input may be energized if the PV arrays are energized. In addition, allow 5 minutes for all capacitors within the main enclosure to discharge after disconnecting the PV100S from AC and DC sources.
To isolate the PV100S:
1.Turn the ON/OFF switch to the OFF position.
2.Open the DC interface disconnect switch.
3.Open the AC interface disconnect switch.
4.Open the utility connection circuit breaker.
5.Install lockout devices on the utility connection circuit breaker and DC disconnect switch.