Chapter 3: Installing the Chassis in an Equipment Rack
Adjusting the Equipment Rack Brackets
The chassis has two
You adjust the brackets by removing them and
Position A, the default position, positions the chassis so that the front of the unit is flush with the front of the equipment rack.
Position B recesses the front of the chassis by 27.39 mm (1.1 in).
Positions C to E extend the front of the chassis beyond the front of the rack from 27.39 mm (1.1 in) to 140.85 mm (5.545 in).
Position F installs the chassis with the rear panel flush with the front of the equipment rack.
To install the rack mount brackets in position “E,” you have to remove the two chassis screws from the
The dimension (X) between the front panel and the rack rails is given for each rack mounting bracket position in Table 20.
Table 20. Front Panel to Rack Rail Dimensions
Figure # | Front Panel Position | Dimension X | |
Front Panel to Rack Rail | |||
|
| ||
|
|
| |
35 | A | 3.69 mm (0.145 in) | |
| (Factory Installed - Flush) |
| |
|
|
| |
35 | B | ||
| (Recessed) |
| |
|
|
| |
35 | C | 27.39 mm (1.078 in) | |
|
|
| |
35 | D | 47.71 mm (1.878 in) | |
|
|
| |
35 | E | 140.85 mm (5.545 in) | |
|
|
| |
36 | F | 374.16 mm (14.731 in) | |
| (Reverse Position) |
| |
|
|
|
80