SwitchBlade x8106 Chassis Switch Installation Guide

Installing the AT-SBxPWRSYS1 AC System Power Supply

For background information on the AT-SBxPWRSYS1 Power Supply, refer to “AT-SBxPWRSYS1 AC Power Supply” on page 53. The chassis must have at least one AT-SBxPWRSYS1 Power Supply.

Warning

The electronic components in the AT-SBxPWRSYS1 Power Supply can be damaged by electro-static discharges (ESD). Follow the procedure in “Protecting Against Electrostatic Discharge (ESD)” on page 90 to guard against ESD damage when unpacking and installing the power supply.

To install the AT-SBxPWRSYS1 Power Supply, perform the following procedure:

1.Choose a slot for the AT-SBxPWRSYS1 Power Supply in the chassis.

You may install it in either slot C and D, shown in Figure 46. The first AT-SBxPWRSYS1 Power Supply should be installed in slot D, because the slot does not have a blank power supply panel.

Slot A

Slot B

Slot C

Slot D

AT-SBxPWRPOE1 AT-SBxPWRPOE1 AT-SBxPWRSYS1 AT-SBxPWRSYS1

Power Supply

Power Supply

Power Supply

Power Supply

Figure 46. Power Supply Slots

Caution

The AT-SBxPWRSYS1 Power Supply will not work in slot A or B.

2.If the chassis already has a power supply in slot D, remove the blank power supply panel from slot C by lifting the blank panel handle and sliding it out of the slot, as shown in Figure 47 on page 92.