Allied Telesis X8106 manual Preparing the Equipment Rack

Models: X8106

1 240
Download 240 pages 38.86 Kb
Page 73
Image 73

SwitchBlade x8106 Chassis Switch Installation Guide

Preparing the Equipment Rack

To prepare the equipment rack for the AT-SBx8106 Chassis, perform the following procedure:

Caution

The chassis is heavy and should be mounted as low as possible in the equipment rack to maximize vertical stability.

1.Reserve 190.0 mm (7.5“) of vertical rack space for the installation of the AT-SBx8106 Chassis, as shown in Figure 29 on page 74.

2.Do not mount any equipment within 152.4 mm (6”) above this space during installation. This additional vertical space is temporary and allows you enough room to lift and tilt the chassis into its position in the equipment rack without striking other equipment. You may use this additional space for other network equipment after the chassis is installed.

73

Page 73
Image 73
Allied Telesis X8106 manual Preparing the Equipment Rack