CHAPTER 2: Getting Started: Twisted Pair Networks

4. The Autotest screen is displayed while Autotest is running.

The Autotest and the Cable name are displayed at the top of the screen. A gauge indicates the test progress. Tests will be listed with their individual

(PASS) or

(FAIL) results as soon as a test is completed.

Once all tests have been performed, the overall test Result: is displayed as PASS or FAIL.

NOTE

The list of tests varies depending on the kind of Autotest that was performed.

An Autotest will PASS if all the selected tests meet the specified criteria. An

Autotest will FAIL if one or more selected tests failed.

2.6.1SAVING TWISTED PAIR AUTOTEST RESULTS

1.Press (Save) from the Autotest screen to open the SAVE AUTOTEST screen, where the Autotests can be stored into OMNIScanner’s memory.

2. The Project field contains the name of the project.

29

Page 31
Image 31
Black Box TS1002A, TS1003A, TS1000A-R5 manual Saving Twisted Pair Autotest Results