Rack Installation

Before you Power Up the Rack

Introduction

This procedure will detail the necessary steps to perform

 

BEFORE bringing the loaded Rack online.

Rack

The Rack is secured properly.

Checklist

 

 

The power cord is connected.

Rack position “Card 0” contains the latest Switch Card

q(Model 3100) loaded.

The appropriate 50-pin female connectors are connected to the Rack backplane and wired to the DEFINITY ECS and PSTN.

Safety

Checklist

 

IMPORTANT SAFETY INSTRUCTIONS

 

Do not install this product near water, for example, in

 

a wet basement location.

 

Do not overload wall outlets, as this can result in the

 

qrisk of fire or electrical shock.

 

Do not attach the power supply cord to building

 

surfaces. Do not allow anything to rest on the power

 

cord. Do not locate this product where the cord will

 

qbe abused by persons walking on it.

 

Do not operate the system if chemical gas leakage is

 

suspected in the area. Use telephones located in some

 

other safe area to report the trouble.

Power Up

If the above checklist is OK, plug the Rack into the AC

 

 

outlet.

 

Issue 1 October 1998 3-17

Page 53
Image 53
Lucent Technologies 3100, 3000 manual Before you Power Up the Rack, Introduction