Installing Switch Cards

 

Installing Switch Cards

Introduction

This chapter explains the steps necessary to quickly install

 

and configure new Model 3100 Switch Cards in the Rack.

Important

qWhen setting up the Rack for the first time, place the

Information

first 3100 Switch Card in Rack position labeled Card

 

0. (This is the slot furthest from the power supply)

 

Note: This is required for the Rack to communicate

 

with the Switch Management Interface software on

 

your PC.

Subsequent Switch Cards may be placed anywhere in

qthe Rack. (Slots 1 to 11)

Switch Cards can be “hot-swapped” as necessary for replacement or upgrading. This means that cards can be added or removed without powering down the entire Rack. This also allows other cards within the

qRack to remain on-line.

To “hot-swap” a Card that is currently in use, use the Make Busy feature. The Make Busy feature prevents dropping calls by monitoring line status. When the remote user ends a call, the Switch Management Interface automatically takes the card offline so it cannot connect again. The Switch Card can then be safely removed if necessary.

4-2Issue 1 October 1998