Upgrading Your Server
Removal
1.See section "Preparing for Installation and Removal" described earlier to prepare.
IMPORTANT: The remote management card logic monitors and logs system voltage changes. When removing the RMC from the mother board, you may experience a 3 - 4 second delay from the time your system powering down.
2.Pull out the server from the rack.
3.Open the logic cover.
4.Open the levers on the both sides of the RMC connector to unlatch the RMC.
5.Remove the RMC from the connector.
6.Run BIOS SETUP utility and check to see that menus related to the RMC are not displayed in the Server menu.
See Chapter 4 for details.
7.Run BIOS SETUP utility and select "Yes" for [Reset Configuration Data] in the [Advanced] menu.
This setting is required to change the hardware configuration data. See Chapter 4 for details.
8.Override installation of NEC ESMPRO Agent if installed.
To correct the system information and event log from the management PC, NEC ESMPRO Agent must be installed in the server.