Grounding Joined Cabinets

Open the door of each cabinet. Locate the grounding stud at the front/side of each frame. Remove the top nut, lock washer, and flat washer from each stud (if attached, see Figures 5).

1.Locate the grounding cable (part of the field kit, located in a small bag which is fastened to the UPS cabinet in the customer terminal area).

2.Mount the grounding cable as shown in Figure 5, attaching it to the frame of each cabinet using the hardware previously removed.

GROUNDING CABLE

HARDWARE REMOVED BEFORE PLACING LUG OVER GROUND STUD

FRONT

PERMANENTLY

ATTACHED

CABINET BASE HARDWARE (side view)

Figure 5. Cabinet-to-Cabinet Grounding