Completing the Installation Checklist

The final step in installing the UPS system is completing the following Installation Checklist. This checklist ensures that all hardware, cables, and other equipment have been completely installed . Completing all items on the checklist will ensure a smooth installation. Make a copy of the Installation Checklist before filling it out, and retain the original.

After the installation is complete, a service representative will be able to verify the operation of the UPS system and commission it to support the critical load. The service representative cannot perform any installation tasks other than verifying software and operating setup parameters. Service personnel may request a copy of the completed Installation Checklist to be sure you have completed all applicable equipment installation.

NOTE: The Installation Checklist MUST be completed prior to starting the UPS system for the first time.

18

Powerware BPIII Harsh Environment UPS 50--75 kV Installation and Operation

164291261 Rev. F 111503

Page 26
Image 26
Powerware 5075 kVA operation manual Completing the Installation Checklist