Migration from DEFINITY Server R to S8700
The full migration from a G3r to an
1.Decide which EPNs are to be IPSI connected, and replace processor complexes with IPSIs.
2.Install servers.
3.Install Ethernet switches.
4.Install UPS units.
5.For
6.Connect the duplication links.
7.Connect the servers and the IPSIs to the control LAN.
8.Sequentially bring up the duplicated servers.
Figure 43: S8700-series Servers (fiber-PNC configuration) shows the completion of Phase 1, an S8700 fiber-PNC system that supports only traditional endpoints.
Figure 43: S8700-series Servers (fiber-PNC configuration)
Note:
In the traditional PBX system, signaling and bearer traffic for all calls connects through the TDM buses within Port Networks and the ATM or traditional center stage