Installation Tasks Checklist
To perform the actual switch installation, the site implementation engineer must perform the following
tasks, which are detailed in this section.
Caution Be sure to review the Safety Information on page 1-9 before starting the installation and during the
installation process. Check the installation site to verify the installation of cabinet power feeds, rails, and
grounding.
Step 1 Unpack the equipment and inspect for any shipping damage. Any ship ping damage should be reported
to the shipping company.
Step 2 Verify that the equipment shipped matches the packing list.
Step 3 Mark the rack and install the mounting rails.
Step 4 Physically install the switch in the rack.

Safety Information

The following safety guidelines are provided to ensure both personal safety for the user and to protect
the system from potential damage. These precautions cover the fol lowing categories:
Precautions for Rack-Mountable Products
Protecting Against Electrostatic Discharge
Electrical Safety Precautions
Precautions fit into one of three categories:
Note A textual callout designed to emphasize:
Tasks of particular importance.
Tips and reminders to maximize the use of the equipment.
Caution Potential for damage to system equipment. Damage to the system caused by the user may have potential
warranty implications.
Warning
Potential for personal injury.

Precautions for Rack-Mountable Products

Warning
Installing system components in a rack without the front and side stabilizers installed could cause