Installation Tasks Checklist

To perform the actual switch installation, the site implementation engineer must perform the following tasks, which are detailed in this section.

Caution Be sure to review the Safety Information on page 1-9before starting the installation and during the installation process. Check the installation site to verify the installation of cabinet power feeds, rails, and grounding.

Step 1 Unpack the equipment and inspect for any shipping damage. Any shipping damage should be reported to the shipping company.

Step 2 Verify that the equipment shipped matches the packing list.

Step 3 Mark the rack and install the mounting rails.

Step 4 Physically install the switch in the rack.

Safety Information

The following safety guidelines are provided to ensure both personal safety for the user and to protect the system from potential damage. These precautions cover the following categories:

Precautions for Rack-Mountable Products

Protecting Against Electrostatic Discharge

Electrical Safety Precautions

Precautions fit into one of three categories:

Note A textual callout designed to emphasize:

Tasks of particular importance.

Tips and reminders to maximize the use of the equipment.

Caution Potential for damage to system equipment. Damage to the system caused by the user may have potential warranty implications.

Warning Potential for personal injury.

Precautions for Rack-Mountable Products

Warning Installing system components in a rack without the front and side stabilizers installed could cause the rack to tip over. Therefore, always install the stabilizers before installing components in the rack.

Cisco SFS 7012 InfiniBand Server Switch Hardware Users Guide

 