DEFINITY Enterprise Communications Server Release 6
Maintenance for R6vs/si
555-230-127 Issue 1
August 1997
Maintenance Object Repair Procedures

Page10-1324TDM-BUS (TDM Bus)

10
System Technician-Demanded Tests:
Descriptions and Error Codes

Use the list configuration control comman d to find the Tone-Clock circuit pack

code of the system, and then proceed to look for the Short and Long Test

Sequences according to the Tone-Clock circuit pack code.

Always investigate tests in the order presented in the following tables when

inspecting errors in the system. By clearing error codes associated with the

SAKI Reset Test

, for example, you may also clear errors generated from other tests in

the testing sequence.
Table 10-457. TEST #297 Digit Detection Test
Error
Code Test
Result Description/ Recommendation
none,
1001
2100
ABORT Could not allocate the necessary system resources to run this test.
1005 ABORT Since this test is valid only on the non-control channel bus, it aborts
execution when run on the control channel bus. This is a valid response.
Use the status system command to verify which bus is the contr ol c hannel
bus.
2000 ABORT Response to the test request was not received within the allowable time
period.
1. Retry the command at 1-minute intervals a maximum of 5 times.
none FAIL This failure indicates that communication on the Non-Control Channel is not
reliable.
1. Execute the command again.
2. If the problem persists, test the Tone-Clock circuit pack and Tone
Detector circuit pack to make sure the y are healthy. Refer to TONE-BD
(Tone-Clock Circuit Pack), TONE-PT (Tone Generator), GPTD-PT
(General Purpose Tone Detector Port), and DTMR-PT (Dual Tone
Multifrequency Port).
3. Execute the command again.
4. If the probl ems persists, refer to the ‘‘TDM Bus Fault Detection and
Isolation Procedure’’ described earlier.
PASS The non-control channel bus is operational.
Continued on next page