Setting System Configuration Data

Installation

 

 

 

 

Setting System Configuration Data

Set system configuration data of the newly installed ATM Switch from the MAT connected to it.

Refer to the Command Manual for the commands from the MAT.

Operation Check Before performing an operation test, make sure that no error response has been output after setting configuration data (see above).

This section describes the procedures for performing an operation test after the

ATM Switch is installed.

ATM Switch Alarms

Check for the ATM Switch hardware errors by entering a command from the MAT.

The following hardware operation tests should be performed:

Switch/CPU card

Line cards

Fan unit

Power unit

1.Enter the command for performing the hardware operation test. The command should be entered as follows:

DISPLAY alarm[RETURN]

2.After entering the command, make sure only the prompt is displayed on the MAT screen. A response is displayed only when an error has been detected.