Installation | Setting System Configuration Data |
|
|
|
|
Line Interface Test
Test the line interface of the line cards installed in the ATM Switch by entering a command from the MAT.
1.Enter the command for performing the line operation test. The command should be entered as follows:
DISPLAY line[RETURN]
2.After entering the command, response of the lines for which line cards are installed is displayed.
3.Make sure that “GOOD” is the response for all lines for which line cards are installed. No response is displayed for a line for which no line card is installed. This completes the operation test. The ATM Switch can now be used properly.
| NOTE |
|
| Follow the instructions below when using the equipment in a country or region |
|
| |||
|
|
| where it must conform to EMI VCCI Type 1, FCC Class A, or EN55022 Class A. | |
|
|
|
| |
|
|
| ||
|
|
|
| ■ Coaxial cable |
|
|
|
| As shown in the illustration below, install a ferrite core near the connector so |
|
|
|
| the cable makes a loop. |
|
|
|
|
|
|
|
|
|
|
Figure 7-14: Ferrite Core Installation
■
❑Use a metal connector
❑Use a shielded cable
❑Securely fasten the metal connector to the main unit
Centillion 1200N ATM Switch User Manual | |