A-BOOM PRE-DELIVERY INSPECTION CHECKLIST

A-BOOM PRE-DELIVERY INSPECTION CHECKLIST

Pre-Operation Inspection: After Assembly is complete. Check the following items before operating the unit to assure that they are properly assembled. (See following page 1-4 for component location)

Saftey Equipment:

-----Operators Manual is with Unit.

-----The Safety Decals are installed as listed in the Assembly Manual.

-----Valve operation plate is installed.

-----Operators cage or Tractor Cab is in place. (Item 1 page 1-5)

-----Deflectors are installed on the Mower Head. (Item 2 page 1-5)

-----Tractor Rops or Cab with seatbels installed properly.

Frame and Boom:

-----Axle Plate Bolts are torqued to 240 ft. lbs. (Item 3 page 1-5)

-----Boom Rest Axle Plate Bolts are torqued to 240 ft. lbs.

-----Front Rail Bolts are torqued to 170 ft. lbs. (Item 17 page 1-5)

-----Front Support Bolts are torqued to 240 ft. lbs. (Item 4 page 1-5)

-----Hydraulic Tank mounting Pins / Bolts in place correctly.

-----Boom Main Pins are torqued to 170 ft. lbs.

-----King Pin Retaining Nut is properly locked in place.

-----All Welds inspected toinsure proper welds and locations.

Hydraulic System:

-----Oil Level in Hydraulic Tank is within the sight gauge. (Item 5 page 1-5)

-----Hose connections are tightented according to specifications.

-----Hoses do not have any kinks or twist in them.

-----Front Pump Shaft adapter bolts are tight. (Item 6 page 1-5)

-----Front Pump Shaft Coupler / Drive Shaft is lubricated and has an anti-seize compound on the Splines of Pump and Shafts. (Item 7 page 1-5)

-----The Pump Drive Shaft has correct alignment.

-----Suction Hose has no leaks or kinks.

Rotary Mower Head:

-----Skid Shoe Bolts are torqued to 120 ft. lbs. (Item 8 page 1-5)

-----Spindle Housing Bolts are torqued to 400 ft. lbs. (Item 9 page 1-5)

-----The Spindle Housing is properly lubricated. (item 10 page 1-5)

-----Motor Bolts are torqued to 120 ft. lbs. (Item 11 page 1-5)

-----Blade Carrier (Bar) Bolts torque to 400 ft. lbs. (Item 12 page 1-5)

-----All Blade Bolts are torqued, the retainings Pins are in place. (item 13 page 1-5)

-----Blades Swing freely. (Item 14 page 1-5)

A-Boom (JD 6615 / 7615 Asy Instruction Manual) 07/03

© 2003 Alamo Group Inc.

Section1 - 3

Page 15
Image 15
Alamo DSEB-D16/SAS A-Boom Pre-Delivery Inspection Checklist, Saftey Equipment, Frame and Boom, Hydraulic System