Alamo DSEB-D16/SAS Frame Rail Installation, Pre-Installing Frame Rails continued, Alamo Group Inc

Models: DSEB-D16 DSEB-D16/SAS

1 119
Download 119 pages 20.92 Kb
Page 40
Image 40
Stabilizer up

Frame Rail Installation

Pre-Installing Frame Rails: (continued)

11.Raising Frame Stabilizer Kit Up Under Tractor. Using a Floor Jack slide Stabilizer Kit under Tractor right behind the front wheels. (See Figure 17). Note the Floor Jack used here has had channel built for it that cradles the square shape, this is also good for supporting the frame rails during assembly. Using Jack helps to align Stabilizer to frame rails. This is shown on a 2 WD Tractor for illustration and is the same for the 4

WD

12.Align Stabilizer Kit. Raise Stabilizer Kit with the Floor Jack up untill it is flush up against the Stabilizer Gusset Support that should already be bolted to the frame from earlier installation steps (See Figure 18). This should be this way on the RH and LH side. DO NOT Weld Gusset to Stabilizer yet this will be done later. Secure the Stabilizer kit to the Frame Rails with C-Clamps on both LH and RH (See Figure 19). You may leave the Floor Jack or remove it.

13.Align Frame Rails on Front Mount Pads. Locate the Front Frame rails on the mount pad so that there is room for the Bolt heads to clear the Frame Rail. Here we have wedged a Screwdriver with a 1/4" shank between the Bolt Head and the Frame Rail. Anything about that size can be used to keep enough distance so bolt can be removed and reinstalled without interference. Use a C- Clamp to hold it in place when aligned. Do this on Both the RH and LH side. (See Figure. 20)

Stabilizer up

against Gusset

C-Clamps

Figure 19

Figure 17

Stabilizer Gusset

Machete

Frame Rail

Stabilizer Kit

Figure 18

Frame Rail
C-Clamp
(Front)

 

 

1/4"

Front Rail
Shanked
Screwdriver
Mounting Pad

 

Figure 20

A-Boom(JD 6615/ 7615 Asy Instruction Manual) 07/03

© 2003

Alamo Group Inc.

Section 4 - 11

 

Page 40
Image 40
Alamo DSEB-D16/SAS Frame Rail Installation, Pre-Installing Frame Rails continued, Alamo Group Inc, C-Clamp, Front, Shanked