Chapter3 Managing ITP Networks Using SGM
Working with Links
3-204
Cisco Signaling Gateway Manager User Guide
78-15589-01
Send Threshold% —Indicates when a cItpSpLinkSentUtilChange is to be
generated for the link, as a percent of its total send capacity. For example, if
Send Plan Capacity is 64000 bits per second, and Send Threshold % is 50,
then a cItpSpLinkSentUtilChange notification is generated when the link
reaches 50% of 64000, or 32000 bits per second.
Receive Plan Capacity—Planned capacity of the link to receive, in bits per
second.
For a link of type Serial or HSL, available bandwidth for the link.
For a link of type SCTPIP, set on the ITP using the plan-capacity CS7
link configuration command.
If Receive Plan Capacity is not set on the ITP for this link, this field
displays the value 0.
For a link of type Other, this field always displays the value 0.
Receive Utilization—Amount of the link’s receive capacity being used, as a
percentage or in Erlangs (as set in the Preferences window), calculated using
the following formula:
Receive Utilization = (Bits Received Per Sec)/Receive Plan Capacity
This field initially displays the phrase Waiting for second poll. After two
polling cycles, SGM populates this field with actual calculated rates.
For a link of type SCTPIP or Mixed, if Receive Plan Capacity is not set
on the ITP for this link, this field displays the phrase Set Plan Capacity
on ITP.
For a link of type Other, this field always displays the phrase Set Plan
Capacity on ITP.
Receive Threshold %—Indicates when a cItpSpLinkRcvdUtilChange is to
be generated for the link, as a percent of its total receive capacity. For
example, if Receive Plan Capacity is 64000 bits per second, and Receive
Threshold % is 50, then a cItpSpLinkRcvdUtilChange notification is
generated when the link reaches 50% of 64000, or 32000 bits per second.