Table 4 Site Inspection Checklist (continued)
Check either Yes or No. If No, include comment number or date. | Comment or Date | |
8. | Is a network line available? |
|
9. | Is a telephone line available? |
|
10.Are
11. Are floor tiles in good condition and properly braced?
12.Is floor tile underside shiny or painted? If painted, judge the need for particulate test.
Power and Lighting |
|
| |
Number | Area or Condition | Yes | No |
13. | Are lighting levels adequate for maintenance? |
|
|
14. | Are AC outlets available for servicing needs (for example, laptop)? |
|
|
15. | Does the input voltage correspond to equipment specifications? |
|
|
15a. | Is dual source power used? If so, identify types and evaluate |
|
|
| grounding. |
|
|
16. | Does the input frequency correspond to equipment specifications? |
|
|
17. | Are lightning arrestors installed inside the building? |
|
|
18. | Is power conditioning equipment installed? |
|
|
19. | Is a dedicated branch circuit available for equipment? |
|
|
20. | Is the dedicated branch circuit less than 75 feet (22.86 m)? |
|
|
21. | Are the input circuit breakers adequate for equipment loads? |
|
|
Safety |
|
|
|
Number | Area or Condition | Yes | No |
22. | Is an emergency power shutoff switch available? |
|
|
23. | Is a telephone available for emergency purposes? |
|
|
24. | Does the computer room have a fire protection system? |
|
|
25. | Does the computer room have antistatic flooring installed? |
|
|
26.Do any equipment servicing hazards exist (loose ground wires, poor lighting, and so on)?
Cooling |
|
|
Number | Area or Condition | Yes No |
27.Can cooling be maintained between 5°C (41 °F) and 35°C (95 °F) (up to 1,525 m/5,000 ft)? Derate 1°C/305 m (34 °F/1,000 ft) above 1,525 m/5,000 ft and up to 3,048 m/10,000 ft.
28.Can temperature changes be held to 5°C (9 °F) per hour with tape media? Can temperature changes be held to 20°C (36 °F) per hour without tape media?
29.Can humidity level be maintained at 40% to 55% at 35°C (95 °F) noncondensing?
30. Are
Storage
Sample Site Inspection Checklist | 11 |