DEFINITY Enterprise Communications Server Release 5
Maintenance and Test for R5vs/si
555-230-123 Issue 1
April 1997
Maintenance Object Repair Procedures
Page10-221BRI-SET, ASAI-ADJ, BRI-DAT
10
SPID Facility Test
This test is used to verify the wiring and operation of the signaling link between
the switch and a endpoint or adjunct on a BRI inte rface. This test is not
executed from the administration terminal, but rather is executed by using a
BRI test set equipped with a display. The test set may replace the BRI set,
ASAI or AT&T adju nct under test by p lugging it into th e same jack or by br idging
it onto the wiring at some point between the switch and the endpoint (or adjunct),
thereby creating a pseudo-BRI multipoint configuration.
When plugged into the port in this manner, the test set establishes a signaling
link connection with the switch and attempts to complete SPID initialization by
using the Service SPID administered for the system (see the System
Maintenance Administration Form). If the test set displays the correct
administered port address for the endpoint or adjunct under test, the test passes
(see Service SPID Display which follows). If after one-minute nothing is displayed
on the test set, the test fails.