Maintenance Object Repair Procedures

Page10-10AC-POWER

10
Error Log Entries and Test to Clear Values

Refer to the appropriate test description and follow the recommended

procedures.

AC Power Query Test (#78)
1. Run the Short Test Sequence first. If all tests pass, run the Long Test Sequence.

Table 10-3. AC Power Error Log Entries

Error
Type Aux
Data Associated Test Alarm
Level On/Off
Board Test to Clear Valu e
010 Any Any Any test environment P sh r 1
513 Any A C Powe r Query
Test (#78) WARNING OFF test environment P sh r 1
Table 10-4. TEST #78 AC Power Query Test
Error
Code Test
Result Description / Recommendation
1000 ABORT System resour ces required to run this test are not available.
1. Retry the command at 1-minute intervals a maximum of 5 times.
2000 ABORT Response to the test request was not received within the allowable time
period.
1. Retry the command at 1-minute intervals a maximum of 5 times.
2. If the test continues to ABORT with Error Code 2000, check for system
powering problems with the A carrier (PPN or EPN). Resolve all
DC-POWER alarms. Then, repeat the test.
3. If the test continues to ABORT with a 2000 Error Code, resolve all
DUPINT (Duplication Interface) errors in a high or critical reliability
system PPN, PR-MAINT (Maintenance/Tape Processor) errors in a
standard PPN, or MAINT (EPN Maintenance circuit pack) errors in an
EPN. Repeat the test.
2029 ABORT Internal syst em error
1. Retry the command at 1-minute intervals a maximum of 5 times.
Continued on next page