DEFINITY Enterprise Communications Server Release 5
Maintenance and Test for R5vs/si
555-230-123
Issue 1
April 1997
Maintenance Object Repair Procedures
Page10-1315SW-CTL (Switch Control)
10
Notes:
a. Refer to DATA-BD (Network Control Circuit Pack) Maintenance
documentation for a description of these tests.
b. Refer to DATA-CHL (Network Control Channel) Maintenance
documentation for a description of these tests.
Control Channel Interface Test (#92)
Loop back messages are sent to the Switch Control via the i nterface used for
control channel messages. The messages are returned to the SPE for verification
via the same interface.
Table 10-396. TEST #92 Control Channel Interface Test
Error
Code Test
Result Description/ Recommendation
2012 ABORT Internal system error
2013
2100
none
ABORT Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals a maximum of 5 times.
1029
2014
2015
2016
2017
2018
2020
2022
2024
2025
2051
ABORT Refer to STBY-SPE for a description of these error codes.