Page8-399status bri-port
8
BRI
(cont’d)
0-126 L3-Assigned ext blank Transitory state for BRI
endpoints which support MIM
initialization.
2. Wait for five seconds and
repeat the command. If the
state has not changed,
continue with Step 2.
3. Make sure SP ID
administration on the switch
and endpoint are
consistent. Verify the repair
by executing the status
bri-port PCSSpp
command. Determine that
the L2 state of the signaling
link is L3-Established.
Otherwise, go to Step 3.
4. Try replacing the endpoint.
Verify the repair by
executing the status
bri-port PCSSpp
command. Determine that
the L2 state of the signaling
link is L3-Established.
Table 8-3. Status BRI-Port Command Interpretation Continued
Endpoint
Types TEI
Range Layer 2 State Voice
Extension Service
SPID Description / Recommendation