UPS SYSTEM INSTALLATION

 

UPM 1 Cable 1G1 & 1G2 Orange

Phase A (E1A)

UPM 2 Cable 2G1 & 2G2 Orange

 

UPM 3 Cable 3G1 & 3G2 Orange

 

Phase A

 

UPM 1 Cable 1G1 & 1G2 Brown – Phase B (E2A)

 

UPM 1 Cable 1G1 & 1G2 Yellow

 

 

UPM 2 Cable 2G1 & 2G2 Yellow

Phase C (E3A)

 

UPM 3 Cable 3G1 & 3G2 Yellow

 

Phase B

Phase A

 

Phase B (E2A) – UPM 3 Cable 3G1 & 3G2 Brown

 

 

 

UPM 2 Cable 2G1 & 2G2 Brown – Phase B (E2A)

 

 

 

 

AC Input to UPMs

NOTE Two cable lugs will be connected to each terminal stud. When connecting the cable lugs, install the first lug on the stud with the raised barrel portion facing the back of the cabinet. Install the second lug with the raised barrel portion facing the front of the cabinet.

NOTE On an UPS without CB1, UPM input wiring terminations are in the same positions on the bus bars installed in the place of CB1. NOTE On an UPS configured as an Input Output Module (IOM), UPM input wiring terminations are the same as an ISBM configuration.

Figure 4-11. ISBM Section Input Power Terminal Detail – Separate Rectifier Feed

4−14

EATON Powerware® 9395 UPS (650–825 kVA) Installation and Operation Manual S 164201725 Rev 2 www.powerware.com

Page 60
Image 60
Powerware 650825 kVA operation manual UPM 1 Cable 1G1 & 1G2 Yellow UPM 2 Cable 2G1 & 2G2 Yellow