UPS OPERATING INSTRUCTIONS

7.4.8UPS and Critical Load Shutdown

To perform maintenance or service on the critical load, shut down power to the load:

1.Turn off all equipment that is being powered by the distributed bypass system.

2.Perform the LOAD OFF procedure in paragraph 7.4.10.

The input, output, battery, and bypass backfeed contactors open, and the power module is turned off.

W A R N I N G

Power is present inside the UPS cabinet sections until the upstream input feeder circuit breaker is opened.

3.If the UPSs contain input breakers (CB1), open all UPS input breakers.

4.Open all of the UPSs input and bypass feeder circuit breakers.

7.4.9Charger Control

To turn the battery charger on:

1.Press the CONTROLS pushbutton on the main menu bar. The System Status screen is displayed.

2.On the System Status screen, select the CHARGER command.

3.Press the CONTROLS pushbutton on the System Status menu bar. The Charger Control Command screen is displayed.

4.On the Charger Control Command screen, select CHARGER ON.

5.Press the SELECT pushbutton on the Charger Command menu bar.

To turn the battery charger off:

1.Press the CONTROLS pushbutton on the main menu bar. The System Status screen is displayed.

2.On the System Status screen, select the CHARGER command.

3.Press the CONTROLS pushbutton on the System Status menu bar. The Charger Control Command screen is displayed.

4.On the Charger Control Command screen, select CHARGER OFF.

5.Press the SELECT pushbutton on the Charger Command menu bar.

EATON Powerware® 9395 UPS (650–825 kVA) Installation and Operation Manual S 164201725 Rev 2 www.powerware.com

7−25

Page 167
Image 167
Powerware 650825 kVA operation manual UPS and Critical Load Shutdown