INSTALLING OPTIONS AND ACCESSORIES

NOTE Setup of the Powerware Hot Sync CAN Bridge Card must be performed by an authorized Eaton

Customer Service Engineer. Contact an Eaton service representative to schedule a date.

9.Install wiring between the SCM II terminal block TB2 and the monitoring equipment. See Figure 5-10for terminal block location and Figure 5-11for terminal assignments.

10.Close the front door and secure the latch.

11.Restart the UPS. See Chapter 7, instructions.

System Normal

No Redundancy

On Generator

Bypass Not Available

On Battery

UPS Alarm

On Bypass

Shutdown Imminent

Figure 5-11. Supervisory Contact Module II TB2

NOTE Supervisory contacts are rated at 2.0A at 28 Vdc or 120 Vac and 0.15A at 115 Vdc.

NOTE Supervisory contacts require an external power supply. Internal 24 Vdc is not capable of supplying contact current.

5−14

EATON Powerware® 9395 UPS (650–825 kVA) Installation and Operation Manual S 164201725 Rev 2 www.powerware.com

Page 106
Image 106
Powerware 650825 kVA operation manual Supervisory Contact Module II TB2