Chapter 3

UPS Installation Plan and Unpacking

Use the following basic sequence of steps to install the UPS:

1.Create an installation plan for the UPS system (Chapter 3).

2.Prepare your site for the UPS system (Chapter 3).

3.Inspect and unpack the UPS sections (Chapter 3).

4.Unload and install the UPS sections, and wire the system (Chapter 4).

5.Install features, accessories, or options, as applicable (Chapter 5).

6.Complete the Installation Checklist (Chapter 4).

7.Have authorized service personnel perform preliminary operational checks and start up the system.

NOTE Startup and operational checks must be performed by an authorized Eaton Customer Service Engineer, or the warranty terms specified on page W−1 become void. This service is offered as part of the sales contract for the UPS. Contact an Eaton service representative in advance (usually a two−week notice is required) to reserve a preferred startup date.

3.1Creating an Installation Plan

Before installing the UPS system, read and understand how this manual applies to the system being installed. Use the procedures and illustrations in paragraph 3.2 and Chapter 4 to create a logical plan for installing the system.

3.2Preparing the Site

For the UPS system to operate at peak efficiency, the installation site should meet the environmental parameters outlined in this manual. If the UPS is to be operated at an altitude higher than 1500m (5000 ft), contact an Eaton service representative for important information about high altitude operation. The operating environment must meet the weight, clearance, and environmental requirements specified.

3.2.1Environmental and Installation Considerations

The UPS system installation must meet the following guidelines:

SThe system must be installed on a level floor suitable for computer or electronic equipment.

SThe system must be installed in a temperature and humidity controlled indoor area free of conductive contaminants.

Failure to follow guidelines may void your warranty.

The UPS equipment operating environment must meet the weight requirements shown in Table 3-1and the size requirements shown in Figure 3-1through Figure 3-10.Dimensions are in millimeters (inches).

For Field Installed UPM (FI−UPM) weights and dimensions, refer to the Powerware 9395 Field Installed UPM Mechanical Installation Manual, listed in paragraph 1.8 on page 1−7.

EATON Powerware® 9395 UPS (650–825 kVA) Installation and Operation Manual S 164201725 Rev 2 www.powerware.com

3−1

Page 23
Image 23
Powerware 650825 kVA Creating an Installation Plan, Preparing the Site, Environmental and Installation Considerations