FORM 201.19-NM1 (204)

INSTALLATION INSTRUCTIONS FOR

VMC SERIES AWR/AWMR AND CP

RESTRAINED MOUNTINGS

1.Floor should be level and smooth.

2.For indoor applications, isolators do not normally require bolting. If necessary, anchor isolators to floor through bolt holes in base plate.

IMPORTANT: Isolators must be bolted to substructure and equipment to isolators when used under outdoor equipment exposed to wind forces.

3.Lubricate threads of adjusting bolt. Loosen hold down bolts to allow for isolator adjustment.

4.Block the equipment 1/4" higher than the spec- ified free height of the isolator. To use the isolator as blocking for the equipment, insert a 1/4" shim between the upper load plate and vertical uprights. Lower the equipment on the blocking or shimmed isolators.

5.Complete piping and fill equipment with water, refrigerant, etc.

6.Turn leveling bolt of first isolator four full revo- lutions and proceed to each mount in turn.

7.Continue turning leveling bolts until equipment is fully supported by all mountings and equipment is raised free of the spacer blocks or shims. Remove blocks or shims.

8.Turn leveling bolt of all mountings in either di- rection in order to level the installation.

9.Tighten nuts on hold down bolts to permit a clear- ance of 1/8" between resilient washer and underside of channel cap plate.

10.Installation is now complete.