Preventive Maintenance
Split/splitless capillary inlets
Leaks
For proper inlet operation, it is essential the entire system be leak•tight. The following procedure should be performed in initial checkout, or any time a leak is suspected.
1.Switch off detector!
2.Install an inlet plug (a paper clip or similar•gaugewire) in the same manner as a capillary column.
Figure
Capillary Inlet Plug Installed for Leak Test
3.Adjust the split•flowflow controller to about 60 ml/min.
4.Adjust or set the column head pressure to obtain a column pressure of 138 kPa (20 psi).
gold | INJ B PRES | 2 | 0 | ENTER | Set inlet B pressure to 20 psi. |
|
|
|
5.Shut off septum purge or cap the septum purge vent with a suitable swagelok fitting. Verify that it is shut off with a soap film (bubble) flow meter.
165