POST INSTALLATION TEST

FCCS Network Connection Test

Make sure that the LYR LED flashes at 60-INT.

 

 

 

 

 

 

 

FCH (PA-FCHA) card

When the result of test￿

 

 

 

is OK, the LYR LED￿

 

 

MB

flashes.

 

 

 

 

 

 

 

LYR

Flash

 

 

 

 

EST3 Send

MNT

 

 

 

Remains ON￿

LB

 

Receive Polarity of￿

Mode 8

when available￿

 

EST2

pair-wire is normal

for Ethernet

 

EST1

Receive

 

 

 

DTI

 

 

 

 

 

 

EST0

Link is￿

 

 

 

 

established

 

Remains ON￿LOAD

 

 

FCH

when ready to broadcast￿

Front View

 

data packets

Note

 

 

 

 

 

 

 

Front View

Note: When the FCH is a “Root Bridge”, the LOAD LED remains ON.

Figure 6-7 Fusion Link-Test Results

STEP 4: Return Mode to 8 (standard setting) when the test is complete.

STEP 5: Initialize the FCH (PA-FCHA) card using the MB switch.

Note: Be sure to initialize the FCH (PA-FCHA) card, after changing the setting of the Mode Switch.

3.FCCS Network Connection Test

This section explains how to perform the following connection tests within the Fusion network:

Station-to-Station Connection Test (via FCCS)

ATTCON Connection Test (via FCCS)

Line (LC, ELC, DLC card) Connection Test (via FCCS)

3-party Conference Trunk Function Test (via FCCS)

3.1Station-to-Station Connection Test (via FCCS)

Perform the station-to-station connection test, following the procedure listed below.

Check

3.1.1 FCCS Call Origination Test

STEP 1: Using the MBCT command, make busy all trunks in the route except the trunk to be tested.

STEP 2: Lift the handset of STN A in Node A.

STEP 3: Dial a Telephone Number (STN B) which belongs to another node.

CHAPTER 6

ND-70185 (E)

Page 138

Revision 3.0

Page 153