4.2CommPak Cartridge Installation and Removal

INSTALLING THE COMMPAK CARTRIDGE

The CommPak cartridge contains the operating software for the Multiserver. When a cartridge is not being used, it should be stored in an anti-static bag.

It is assumed that the CCM is installed. You cannot install the CommPak cartridge unless the CCM is installed.

Warning!

Any time that a CommPak is installed or removed from the base unit, be sure that the power cord is unplugged. Failure to do so could result in damage to the CommPak cartridge.

CHAPTER 4: Base-Unit Installation

REMOVING THE COMMPAK CARTRIDGE

If you ever need to remove the CommPak cartridge (such as for upgrading purposes), these are the steps you should follow:

1.Unplug the power card from the ac power socket.

2.Pull out the right side of the extractor handle.

3.Slide out the cartridge. The door will close

EXE

5000

MULTISERVER

EXE

5000

MULTISERVER

Figure 4-2. Step one: Slide the CommPak cartridge into the bottom beveled door. The door will move out of the way. (Do not use the top slot.)

Figure 4-4. Pull out the extractor handle in order to remove the CommPak cartridge.

behind it.

4.3 Power Up the Unit

After the CommPak cartridge is installed in the unit, plug the power cord into the back of the unit and into the wall outlet. The Multiserver will power up and automatically go into a self-test mode (which lasts approximately 30 seconds).

EXE

5000

MULTISERVER

Figure 4-3. Step two: Be sure to push in the cartridge until it is flush against the unit. To fully seat the CommPak cartridge, you will need to exert pressure. There must be no gap between the cartridge and the unit.

4.4 LCD Display

Figure 4-5. Plug in the power cord after the CommPak is installed.

35