Chapter 2 Preparing for Installation
Site Requirements
Site Requirements
To ensure normal operation and avoid unnecessary maintenance, plan your site configuration and prepare your site before installation. Take into account the following criteria:
Note To locate the most reliable channels for your downstream and upstream channel plans, we recommend that you perform a sweep of all available channels for at least a 24 hours to verify the presence or absence of impulse and ingress noise.
•Select forward and reverse channel frequencies from the range specified in your channel plan.
•Verify that your cable network meets system requirements and
•Make sure that the site maintains an ambient temperature of 32 to 104°F (0 to 40°C), and keep the area around the chassis as free from dust as is practical.
AC Power
The AC input of the power supply module uses a power factor corrector that allows the Cisco uBR 3x10 RF Switch to operate on input voltage and frequency within the ranges of 100 to 240 VAC and
50 to 60 Hz.
Note We recommend an uninterruptable power source to protect against power failures at your site. An
See Appendix A, “Specifications and Component Part Numbers,” for system power specifications, including input voltage and operating frequency ranges.
DC Power
The DC input of the power supply module operates at
Note Each
See Appendix A, “Specifications and Component Part Numbers,” for system power specifications, including input voltage and operating frequency ranges.
Cisco
|
| ||
|
|