Installing the server | Routing cables |
DataCenter Rack
For installing the server in the DataCenter Rack at first the cable management system must be mounted. Further informations find you in the Technical Manual of the DataCenter Rack.
2 |
1 |
Figure 9: Routing the cables in the DataCenter Rack
ÊRoute the cables in the articulated cable guide (1) of the cable management system and secure its using the delivered cable ties.
ÊRoute the cables around the cable management guidance (2) (see figure 9 on page 27).
ÊRoute the cables through the cable clips on the right support upright after having inserted the server (see Technical Manual of the Rack).
ÊCheck to see if the server can be pulled out without breaking or even over- stretching the cables.
27 |