2.2Installing the Switchboard System Bypass Module

The SSBM is shipped in separate shipping sections. Each shipping section is bolted to a wooden pallet.

WARNING:

The SSBM shipping sections are extremely heavy. If unloading instructions are

not closely followed, the sections may tip and cause serious injury.

1.Find section labels on each shipping section. Install the shipping sections in numerical order.

CAUTION:

Only insert the forklift jacks where “FORK HERE” signs appear on cabinet packaging.

2.Move the SSBM to final installed location using forklift jacks between the raised supports on the bottom of the unit.

3.Remove side panels from SSBM cabinet to gain access to hardware securing cabinet to pallet.

4.Remove hardware securing cabinet to pallet.

CAUTION:

Lift only at lifting eyes or cabinet damage may occur..

5.Attach suitable hoist to SSBM lifting eyes and lift SSBM cabinet until the cabinet bottom clears the pallet by approximately 3 mm (1/8 in.).

6.Once SSBM cabinet is clear of the pallet, pull the pallet from under the UPS cabinet. Discard or recycle them in a responsible manner.

7.Carefully lower the SSBM cabient until the cabinet base contacts the floor.

8.Remove lifting eyes from SSBM cabient.

9.With the shipping section in their final locations, align SSBM shipping sections.

10.Bolt shipping sections together with supplied hardware and anchor to floor or pad.

11.Install all Bypass, Critical, and Neutral Bus shipping split bus plates. Torque supplied hardware to 30 ft-lbs.

12.Install all Ground Bus shipping split bus plates. Tighten supplied hardware.

13.Run section wiring harnesses through wire trough in rear cabling area and pass into Control section through grommeted opening.

14.Insert harness plugs into match caps in the bottom of the A1 Panel in the Control Section.

2--2

Powerware 9315 Parallel Capacity/Redundant System with PHP SSBM

 

164201373 Rev. A 092402

Page 30
Image 30
Powerware 9315s manual Installing the Switchboard System Bypass Module